22nd Feb 2017

Bigger turnout tonight which is great!

Jobs included taping up all the parts ready to take the epoxy, cutting the wood ready for lamination of the stem, and then a dry run for the clamping itself.

I was keen to keep the strips of wood a long as possible so we can use it to add the mast head onto it, but the height of the frame off the ground restricts how long these can be left, so we’ve gone for the “that fits, lets do that and sort it out later”, approach.

Don’t think this will cause much problem as there is enough wood to attach something onto. At the moment the plan is for the mast head to be removable.

This is the frame that’s been made up for stems.

 

 

 

 

We think it should be warm enough this Wednesday to Epoxy, so that will be the main task on the 1st of March. As can be seen we have borrowed some more sturdy clamps. We think it will be 8 a side.

 

 

 

 

 

We also need to cut out the rest of the planking so the skarfing can be done. If we don’t do this we not have the space to do it later.

Andy has started work on a tiller handle, picture to come next week.